|
Perspectives |
Mechanical Fastenersby Incorrect fastener installation, when used for
securement of the insulation and/or roof membrane, can cause serious roof
problems, including membrane blow-offs. It is a widely accepted practice to use an
approved fastener and plate to secure the roof insulation and/or roof
membrane to the substrate. However,
problems occur when the wrong fastener is used or improperly installed as
discussed in the following scenarios. During a routine roof survey of a large industrial complex, a
partial blow-off of a modified bitumen roof was discovered. The initial review of the damaged roof
components showed the insulation plates and screws were properly placed in
the steel deck and damage likely occurred due to high winds, which exceeded
the roof’s design requirements. The
fasteners and plates were no closer than six inches from the edges of the
insulation, evenly spaced, and did not appear to be over driven. However, while extracting a fastener
counterclockwise to verify its length and condition, it simply spun but did
not back out. The fastener was
apparently stripped out or damaged, so the plate was lifted to aid in the
extraction. As the plate was lifted,
the screw also lifted approximately 1/8”, then stopped and was backed out for
examination. The screw measured 6”
long, showed no corrosion or damage and looked like new. This was the perfect screw if the
insulation was 4.5” to 5” thick, but as this insulation was less than 3”
thick, it didn’t hold. On longer screws the threads do not extend all
the way up the shank, as only 3/4” of deck penetration through the top deck
flange is recommended, so engagement of the bottom rib does not occur. While rib depth does vary, typical depth is 1.5”. Not installing threads up the entire shank
also saves money. The contractor had
utilized fasteners long enough to engage the top and bottom ribs, and in
doing so, the fastener was so long that when the screws penetrated the top
flange, there were no threads to provide constant tension and compression of
the insulation to the deck. Winds had
been lifting the roof system up off the deck in an ongoing ratcheting motion
until the insulation failed at the fastener locations. This roof was less than two-years old when
it failed. During the design phase of a failed mechanically attached
single-ply system, incorrect fastener installation again appeared to be the
culprit. This mechanically fastened reinforced single-ply roof system was
secured to a cast-in-place concrete deck with steel spikes and 2” barbed
plates at 18” on center. The fastening
rate met the manufacturer and code requirements for the timeframe when it was
installed. This particular roof had also survived previous
storms and hurricanes, but eventually failed during such an event. It failed because the fasteners were pulled
from the deck. The system used 3”
drive pins to secure 2” insulation, resulting in 1” fastener embedment. This also met the roofing manufacturer’s
criteria, but a closer look at the drive pin revealed the paint had not been
scraped off the shank of the three fastener compression points, but rather
only the lower two. This indicated
that the fastener was not fully driven into the predrilled hole. This could have been caused by many things: When a hole is predrilled it must be 1/2” deeper
than the fastener penetration to ensure drilling debris does not restrict
penetration. The fastener must be
fully set (i.e. hammered into the hole), and the fastener must be of
sufficient length. A check of the hole
depth showed the predrilled hole was indeed deep enough. The fastener size met the issued
specification, and a check of existing fasteners revealed they were properly
driven, thus ruling out the three requirements described above. The fastener failed because in fact it was not
long enough. Although the membrane
manufacturer stated 1” embedment was adequate, the fastener manufacturer
required 1 1/4 - 1 1/2” embedment.
Fastener withdrawal tests revealed the existing 1” fasteners had 450
to 500 pounds of pull-out resistance, while a 1 1/4” fastener would have 1100
pounds of pull-out resistance and 4000 pounds for a 1 1/2” fastener. This is a huge difference in strength, and ultimately
contributed to this roof failing during a high wind event. In
both cases, the correct fastener was used, but it was not the correct
length. When designing and installing
a roof system, the proper size and type of fastener must be used or failure
can result. Copyright (c) 2005, Benchmark,
Inc., all rights reserved. |
|
|